Logbook
Weekly Report
1st Week Report (19/02/2018 - 25/02/2018)
The first week the team had to do some activities of team building to know their teammates better and have a solid base to grow as a good team.
2nd Week Report (26/02/2018 - 04/03/2018)
The second week the team had to choose the theme of their project: “Vertical Farming” from a list of possibles subjects and they started to do some researches and planing the deadlines and tasks as well as doing the Gantt chart and they continue doing some team building activities.
3rd Week Report (05/03/2018 - 11/03/2018)
The third week the team did some drafts and started to figure out solutions for the design, technicals solutions such as how to water, fed and light the plants.
4th Week Report (12/03/2018 - 18/03/2018)
The fourth week the team showed the black box diagram and they still working on developing ideas for the design and how can it be the technology included. The sustainability, marketing studies started to be developed. During that week apart from working on the project, they had two trip days, visiting one-day “Tresminas” and the other day the Visit of the city center of Porto.
5th Week Report (19/03/2018 - 25/03/2018)
The fifth week the team worked on the 3D draft, schematics (internal, exterior and electrical part), a “provisional” list of materials have been done on it, with an orientation price. For showing to their supervisors apart from the 3D work on CAD, the team built a cardboard box to show their supervisors the idea that the team has for building the vertical farming. Also, the Ethical report has been started with the idea of the “problem statement” and has changed and improved some of the things that they were said to correct about the wiki.
6th Week Report (26/03/2018 - 01/04/2018)
Due to the Easter Holidays, the week was free, so the team just corrected some minor things in the wiki.
7th Week Report (02/04/2018 - 08/04/2018)
The team managed to make a list of the materials that are necessary to build the prototype and project. This list, however not final, will provide a decent ground for listing the possibilities that our product will offer. The list can be found in the deliverables section, although as mentioned previously, it is subject to change and may not be the same list that has been submitted during this week.
Based on the supervisor meeting, the team needs to work on the wiki and that will be the focus in the upcoming weeks.
8th Week Report (09/04/2018 - 15/04/2018)
The team worked extensively to update the wiki. There has been a major improvement on the report page of the wiki and regarding the following sections:
Additionally, the team provided references for every external source found to support the claims on the report page.
9th Week Report (16/04/2018 - 22/04/2018)
The team finalized some mistakes in the wiki and corrected the grammatical issues present there. In the meantime, the team prepared an interim report presentation because this week on 19/04/2018 the team had to present the interim report. The team received mostly positive feedback from the supervisors on the presentation. After the presentation, the team worked to improve the report and the product based on the feedback from the supervisors.
10th Week Report (23/04/2018 - 29/04/2018)
The team improved the original list of materials and did some research about where to find the materials needed. This way, the team added a new part to the list of materials with the providers of them. This way, the university can find out where to look for the materials.
11th Week Report (30/04/2018 - 06/05/2018)
The team finished the improvements on the report on the wiki based on the feedback received on the interim report from the supervisors. Additionally, the team made some extra improvements on the list of materials due to the fact that we were over the budget limit, even though the supervisors decided to grant a sponsorship with some materials from ISEP.
12th Week Report (07/05/2018 - 13/05/2018)
This was the student free week so the team just improved some small grammatical mistakes in the wiki.
13th Week Report (14/05/2018 - 20/05/2018)
The team received the electronic part of the materials and a voucher for Leroy Merlin mechanical parts. Rodrigo and Andres went to pick up the materials from the store and after that, we researched the quality of the materials. We found out that some materials are missing and some materials are different from our demand. We shall discuss with the supervisors for this in the following week.
14th Week Report (21/05/2018 - 27/05/2018)
The team received the mechanical items that were needed to build the prototype. The team also discussed possible changes to the electronic part of the items with the supervisors and we came to a solution and started assembling the prototype. In the marketing class, we received feedback about the wiki and we will update the wiki per request.
15th Week Report (28/05/2018 - 03/06/2018)
The team continued to assemble the prototype and the electronic parts start to function well together. The workers of the prototype are as follows:
Rodrigo and Andres are working on the mechanical parts of the product
Szymon is assembling the electronic parts
Mile is programming the server side code and is preparing the database
Audrey and Anastasia are preparing the flyer and the marketing part of the product
16th Week Report (04/06/2018 - 10/06/2018)
After a programming session, we have boot up the server and the database is functional. Szymon is almost done with assembling and soldering the electronic parts of the product and Andres and Rodrigo are still working on the mechanical parts.
Meetings
1st Meeting (2018-02-22)
Agenda:
Presentation
Modus operandi
Project proposals
Electronic Logbook
Minute:
Introduce here a brief report of the meeting.
2nd Meeting (2018-03-01)
Agenda:
Define “Urban Space”? - do we understand it as a system accessible publicly in the city squares, or do we understand a system for the private purpose, suitable for use in densely occupied city centers?
What are the expected “different size areas” boundaries? - does the scale start from the kitchen countertop and goes to a bookshelf, or does it start on a bookshelf and goes to a glasshouse?
What variety of plants is to be farmed? - Herbs only or perhaps small vegetables like cherry tomatoes just as well? What level of complexity of the crop would be considered to be a success of the project?
Minute:
Start 9:20
6 teachers, Anastasia, Audrey, Mile, Andres, Rodrigo
We use less soil than traditional farming
Urban Space
Requirements
Luis marketing
Ethics
In 2 weeks:
We choose what we want, every decisión we make the place is decided by us and we have to justified, based on our marketing studies, sustainability studies and ethics studies.
After the meeting:
ART Chapter:
Size:
ISSUE 1: Adapting the structure to different sizes
Modularity is the solution with 1m2 more or less.
The size, the water, we need to consider
Variety of plants:
The sustainability part is a success since we don't pollute because the transport is local instead
Hydroponic plants(building H there is a tank)
exotic fruit is complicated(because they are big) gravity is gravity, physalis(exotic fruit little and its expensive in the market)
for home(what we normally eat)
Other:
don't work individually in parallel. Each task not only person. Try to work cooperatively.
There should be something that comes from our mind, it can be innovated only the design, or other things(more efficient)
Gaia( “Caninho das Aromáticas”)→ Visit(herbs, infusions)→ biological farming
CONSIDERATION:
IDEA: Don't use pesticides or fertilizers, and see which adapt better to our climate.
RESEARCH
What to grow,
Write what we find
3rd Meeting (2018-03-08)
Agenda:
2nd Meeting's conclusion about the space and the size of the project
Minimum Viable Product of a modular prototype - what basic prototype would be considered a proof of concept? Shall we have a plant grown in the prototype?
Report updating clarification - how should weekly reports be constructed? What period is considered in one week (Monday - Sunday or Meeting - Meeting)?
Pros and cons of different plant growth solutions
Hydroponics
Aquaponics
Aeroponics
Soil solution
Minute:
6 teachers and Anastasia, Audrey, Andres, Szymon, Rodrigo
In the «weekly report» we have to write down what we have done during the week in one or two sentences, for instance for the first weekly report add the theme we think before choosing vertical farming and the discussions we had.
Also we have to complete the «state of arts».
About the cons of hydroponic plants inside a house is that if it is opened, it generates a lot of humidity and if we closed the plant will need to breathe.
About the cons of aquaponics are difficult to do, so if we mix with vertical farming can lead to a complex project.
Other business:
Modularity: the modules should have the possibility of being connected between them, and also being possible to be disconnected when it is wished.
Some ideas: IKEA hydroponic System, Quinta do Covelo, MiniGarden.com, UrbanGrowth, Strawberries.
4th Meeting (2018-03-15)
Agenda:
Presentation of the idea that we have
Brief description of the black box
Can we add up our own budget to the 100 € and use some equipment from the university(Arduino for example)?
Minute:
How to manage the environment
How to control the plant's needs
How we can manage with 100 € or, how to justify if we need more than the limit
Do a study on sustainability and ethics and put it onto our project
Why indoor production and how much energy will it take for indoor/outdoor
Fixing and improving the state of the art on the wiki
5th Meeting (2018-03-22)
Agenda:
Minute:
The fourth-week report and the “activities” part of the wiki must be filled in
The wiki in the state of art chapter we have to add “Captions”.
In the marketing report, we have to estimate the price of real one(not the prototype, the real size one).
In project management, we must explain the Gantt chart and the SCOPE, not only with pictures.
We need to work on the electrical schematics.
Advice: Think about some kind of air flow for the roots of the plants, to not have much temperature.
6th Meeting (2018-04-05)
Agenda:
Boundaries of the Interim Report / Presentation
Material acquisition procedure:
Are in-town pickups acceptable for reducing delivery costs?
Can we split ordering into multiple rounds?
State of ISEP electrical supplies:
Are minor electrical pieces (resistors, capacitors, diodes, etc.) available for use in small quantities?
Possibilities for the budget increase - are there any? Under what circumstances?
Minute:
Interim report should include: Sustainability, Marketing, Ethics, State of the Art, Black Box, Full Material list, Detailed Schematics
Take consideration of power management as well as cost management
We should improve the wiki
7th Meeting (2018-04-12)
Agenda:
Interim Report
Possible sponsorship - based on the case of the team 2
Postponing the media materials (logo, product name, leaflet…)
Minute:
8th Meeting (2018-04-19)
Agenda:
Minute:
9th Meeting (2018-04-26)
Agenda:
Interim presentation feedback
What to do if, while assembling, we discover that we need more things than in the list of materials?
Future objectives
Minute:
Received both positive and negative feedback regarding the Interim presentation
If we need more materials, we should prepare an updated list if we are in budget and wait for them to arrive
10th Meeting (2018-05-03)
Agenda:
Minute:
11th Meeting (2018-05-17)
Agenda:
Minute:
12th Meeting (2018-05-24)
Agenda:
Different voltage source provided - obtained 2A unit instead o 1A one ordered. Possible risk for other components, as 2A current would exceed their ratings? Clarification would be appreciated.
What can and what cannot be soldered among the electrical components? Why?
Cables, breadboard, and connectors - can we get a reasonable surplus? We've estimated a need for 15 x Female-Female and 10 Male-Female jumper cables, the longer the better.
Missing element from the shopping list - the electrical components box. Was it unavailable?
Workshop: where, when, what are the rules of availability? What equipment is available? Mechanical AND electrical?
Minute:
13th Meeting (2018-05-30)
Agenda:
Minute:
14th Meeting (2018-06-07)
Agenda:
Minute:
Discussion about a solution for waterproof water deposit for the prototype
Proposition of soldering scheme has been presented to the supervisors. After feedback by Paulo, small corrections have been made to improve the soldering paths. The circuit has been executed the same day.
15th Meeting (2018-06-14)
Agenda:
Minute:
We will use the university's WiFi for the final presentation and we got instructions about how to connect our device to that internet
Received feedback about the current flowcharts in the project and information about which other flowcharts to include
The supervisors told us the rules and the timespan of the final presentation
Activities
| Start | End | Task | Description | Who |
| 05.03.2018 | 06.03.2018 | Roles and Divisions | Dividing the team into roles about who to do what | Everyone |
| 08.03.2018 | 09.03.2018 | Gantt Chart | Creating the Gantt chart with the tasks and time according to the team | Mile and Audrey |
| 28.02.2018 | 15.03.2018 | Research | Researching about the problem and the prototype | Everyone |
| 15.03.2018 | 18.03.2018 | Drafts | Creating the vague drafts about the prototype | Everyone |
| 19.03.2018 | 23.03.2018 | Detailed Drafts | Creating the 3D models about the prototype | Rodrigo |
| 24.03.2018 | 05.04.2018 | List of Materials | Preparing the list of materials needed | Everyone |
| 06.04.2018 | 25.04.2018 | Provider searching | Finding the providers for the list of materials | Everyone |
| 26.04.2018 | 20.05.2018 | Polishing and upgrading the report | Upgrading the report while waiting for the materials to be received | Everyone |
| 21.05.2018 | 23.05.2018 | Design of the System | Designing the product based on the materials received | Everyone |
| 22.05.2018 | 28.05.2018 | Server configuration | Configuration of the server to handle the device | Mile |
| 22.05.2018 | | Backend programming | Programming the back-end application for the device | Mile |
| 24.05.2018 | | Mechanics part | Assembling the mechanical parts of the prototype | Rodrigo and Andres |
| 24.05.2018 | | Electronics part | Assembling the electronic parts of the prototype | Szymon and Andres |
| | | Application programming | Programming the Android application | Szymon and Mile |
| 24.05.2018 | You can never finish testing | Testing | Testing if the system works as intended | Everyone |