Logbook

Weekly Report

1st Week Report (19/02/2018 - 25/02/2018)

The first week the team had to do some activities of team building to know their teammates better and have a solid base to grow as a good team.

2nd Week Report (26/02/2018 - 04/03/2018)

The second week the team had to choose the theme of their project: “Vertical Farming” from a list of possibles subjects and they started to do some researches and planing the deadlines and tasks as well as doing the Gantt chart and they continue doing some team building activities.

3rd Week Report (05/03/2018 - 11/03/2018)

The third week the team did some drafts and started to figure out solutions for the design, technicals solutions such as how to water, fed and light the plants.

4th Week Report (12/03/2018 - 18/03/2018)

The fourth week the team showed the black box diagram and they still working on developing ideas for the design and how can it be the technology included. The sustainability, marketing studies started to be developed. During that week apart from working on the project, they had two trip days, visiting one-day “Tresminas” and the other day the Visit of the city center of Porto.

5th Week Report (19/03/2018 - 25/03/2018)

The fifth week the team worked on the 3D draft, schematics (internal, exterior and electrical part), a “provisional” list of materials have been done on it, with an orientation price. For showing to their supervisors apart from the 3D work on CAD, the team built a cardboard box to show their supervisors the idea that the team has for building the vertical farming. Also, the Ethical report has been started with the idea of the “problem statement” and has changed and improved some of the things that they were said to correct about the wiki.

6th Week Report (26/03/2018 - 01/04/2018)

Due to the Easter Holidays, the week was free, so the team just corrected some minor things in the wiki.

7th Week Report (02/04/2018 - 08/04/2018)

The team managed to make a list of the materials that are necessary to build the prototype and project. This list, however not final, will provide a decent ground for listing the possibilities that our product will offer. The list can be found in the deliverables section, although as mentioned previously, it is subject to change and may not be the same list that has been submitted during this week.

Based on the supervisor meeting, the team needs to work on the wiki and that will be the focus in the upcoming weeks.

8th Week Report (09/04/2018 - 15/04/2018)

The team worked extensively to update the wiki. There has been a major improvement on the report page of the wiki and regarding the following sections:

Additionally, the team provided references for every external source found to support the claims on the report page.

9th Week Report (16/04/2018 - 22/04/2018)

The team finalized some mistakes in the wiki and corrected the grammatical issues present there. In the meantime, the team prepared an interim report presentation because this week on 19/04/2018 the team had to present the interim report. The team received mostly positive feedback from the supervisors on the presentation. After the presentation, the team worked to improve the report and the product based on the feedback from the supervisors.

10th Week Report (23/04/2018 - 29/04/2018)

The team improved the original list of materials and did some research about where to find the materials needed. This way, the team added a new part to the list of materials with the providers of them. This way, the university can find out where to look for the materials.

11th Week Report (30/04/2018 - 06/05/2018)

The team finished the improvements on the report on the wiki based on the feedback received on the interim report from the supervisors. Additionally, the team made some extra improvements on the list of materials due to the fact that we were over the budget limit, even though the supervisors decided to grant a sponsorship with some materials from ISEP.

12th Week Report (07/05/2018 - 13/05/2018)

This was the student free week so the team just improved some small grammatical mistakes in the wiki.

13th Week Report (14/05/2018 - 20/05/2018)

The team received the electronic part of the materials and a voucher for Leroy Merlin mechanical parts. Rodrigo and Andres went to pick up the materials from the store and after that, we researched the quality of the materials. We found out that some materials are missing and some materials are different from our demand. We shall discuss with the supervisors for this in the following week.

14th Week Report (21/05/2018 - 27/05/2018)

The team received the mechanical items that were needed to build the prototype. The team also discussed possible changes to the electronic part of the items with the supervisors and we came to a solution and started assembling the prototype. In the marketing class, we received feedback about the wiki and we will update the wiki per request.

15th Week Report (28/05/2018 - 03/06/2018)

The team continued to assemble the prototype and the electronic parts start to function well together. The workers of the prototype are as follows:

16th Week Report (04/06/2018 - 10/06/2018)

After a programming session, we have boot up the server and the database is functional. Szymon is almost done with assembling and soldering the electronic parts of the product and Andres and Rodrigo are still working on the mechanical parts.

Meetings

1st Meeting (2018-02-22)

Agenda:

  1. Presentation
  2. Modus operandi
  3. Project proposals
  4. Electronic Logbook

Minute:

Introduce here a brief report of the meeting.

2nd Meeting (2018-03-01)

Agenda:

Minute:

Start 9:20

6 teachers, Anastasia, Audrey, Mile, Andres, Rodrigo

We use less soil than traditional farming

Urban Space

Requirements

Luis marketing Ethics

In 2 weeks:

After the meeting:

ART Chapter:

Size:

Variety of plants:

Other:

CONSIDERATION:

IDEA: Don't use pesticides or fertilizers, and see which adapt better to our climate.

RESEARCH

3rd Meeting (2018-03-08)

Agenda:

Minute:

6 teachers and Anastasia, Audrey, Andres, Szymon, Rodrigo

4th Meeting (2018-03-15)

Agenda:

Minute:

5th Meeting (2018-03-22)

Agenda:

Minute:

6th Meeting (2018-04-05)

Agenda:

Minute:

7th Meeting (2018-04-12)

Agenda:

Minute:

8th Meeting (2018-04-19)

Agenda:

Minute:

9th Meeting (2018-04-26)

Agenda:

Minute:

10th Meeting (2018-05-03)

Agenda:

Minute:

11th Meeting (2018-05-17)

Agenda:

Minute:

12th Meeting (2018-05-24)

Agenda:

Minute:

13th Meeting (2018-05-30)

Agenda:

Minute:

14th Meeting (2018-06-07)

Agenda:

Minute:

15th Meeting (2018-06-14)

Agenda:

Minute:

Activities

Start End Task Description Who
05.03.2018 06.03.2018 Roles and Divisions Dividing the team into roles about who to do what Everyone
08.03.2018 09.03.2018 Gantt Chart Creating the Gantt chart with the tasks and time according to the team Mile and Audrey
28.02.2018 15.03.2018 Research Researching about the problem and the prototype Everyone
15.03.2018 18.03.2018 Drafts Creating the vague drafts about the prototype Everyone
19.03.2018 23.03.2018 Detailed Drafts Creating the 3D models about the prototype Rodrigo
24.03.2018 05.04.2018 List of Materials Preparing the list of materials needed Everyone
06.04.2018 25.04.2018 Provider searching Finding the providers for the list of materials Everyone
26.04.2018 20.05.2018 Polishing and upgrading the report Upgrading the report while waiting for the materials to be received Everyone
21.05.2018 23.05.2018 Design of the System Designing the product based on the materials received Everyone
22.05.2018 28.05.2018 Server configuration Configuration of the server to handle the device Mile
22.05.2018 Backend programming Programming the back-end application for the device Mile
24.05.2018 Mechanics part Assembling the mechanical parts of the prototype Rodrigo and Andres
24.05.2018 Electronics part Assembling the electronic parts of the prototype Szymon and Andres
Application programming Programming the Android application Szymon and Mile
24.05.2018 You can never finish testing Testing Testing if the system works as intended Everyone